Section 48D in Plain English: What the 48D Construction Deadline of Dec 31, 2026 Means
Direct answer: The 48D construction deadline means a chip or chip-equipment project gets no Section 48D credit if its construction begins after December 31, 2026. Construction only has to start by then, under the physical work test or the 5% safe harbor; property can be placed in service years later. No extension had been enacted as of November 19, 2026. [1] [2]

This explainer reads the rule itself: the statute, the Treasury final regulations and the official bill records, checked on November 19, 2026. For the credit rate, who can claim it and a running status table, use our Section 48D deadline tracker; this page explains what the date actually requires. It is not tax advice.
What the 48D construction deadline says
Section 48D(e) of the tax code is one sentence: the credit "shall not apply to property the construction of which begins after December 31, 2026" [2]. The final regulations repeat it: no credit for property of an advanced manufacturing facility if construction of that property begins after that date [3].
Three things follow from the wording:
- It is a start date, not a finish date. Nothing in 48D(e) says the plant must be built, equipped or running by the end of 2026.
- The credit is still claimed later. The IRS says the credit is figured on qualified property when it is placed in service, reported on Form 3468 [1]. A project that started in 2026 can claim it in a later year.
- A start in January 2027 gets nothing under current law. There is no phase-down; the statute simply stops applying to later starts [2].
What "begins construction" means in the regulation
The final regulations (26 CFR 1.48D-5, adopted in T.D. 10009, October 23, 2024) give two ways to show construction began [3] [4]:
1. Physical work test
Construction begins when "physical work of a significant nature" begins. The regulation says the test looks at the nature of the work, not its cost, and sets no minimum dollar or percentage amount [3]. Its examples:
- On-site: excavation for the foundation and pouring the concrete pads of the foundation.
- Off-site: manufacturing semiconductor manufacturing equipment, but only under a binding written contract and only if the equipment is not held in the manufacturer's inventory.
It does not count preliminary activities: planning or design, securing financing, exploring, research, permits and licensing, surveys, environmental and engineering studies, or clearing a site, even when those costs end up in the property's basis [3].
2. Five percent safe harbor
Construction is treated as begun if the taxpayer pays or incurs 5% or more of the total cost of the property. All costs properly included in basis count. If the project's final cost overruns so the early spending falls below 5%, the safe harbor covers only some of the separate facilities in a multi-facility project, not the whole thing [3].
Our upcoming page on the begin-construction rules will go deeper into units of property and binding contracts.
After the start: the continuity requirement and the 10-year window
Starting is not enough. Under either method, the taxpayer must then keep up "continuous construction" (continuing significant physical work) or "continuous efforts" to advance toward completion. The regulation says the IRS "will closely scrutinize" this and decides it on facts and circumstances [3].
Factors the regulation lists as showing continuous efforts include paying or incurring more of the cost, signing binding contracts for future work, obtaining permits, and doing significant physical work [3]. It also lists delays that do not break continuity, among them severe weather, natural disasters, permit delays, electrical or water supply delays, custom equipment delays, supply shortages, financing delays and specialized labor shortages [3].
The simplest route is the continuity safe harbor: continuity is deemed met if the property is placed in service no more than 10 calendar years after the calendar year construction began [3]. Applying the regulation's own example to a 2026 start, that means placed in service by December 31, 2036. Excusable delays do not extend that 10-year date [3].
Is an extension of the 48D construction deadline coming?
As of November 19, 2026, we found no enacted extension. The official Congress.gov records show [5] [6]:
| Bill | Would move the date to | Introduced | Latest action on Congress.gov |
|---|---|---|---|
| H.R. 3204 (BASIC Act) | Dec 31, 2030 | May 5, 2025 | Referred to House Ways and Means, May 5, 2025 |
| H.R. 6055 (SEMI Investment Act) | Dec 31, 2031 | Nov 17, 2025 | Referred to House Ways and Means, Nov 17, 2025 |
A Thomson Reuters Checkpoint report dated November 19, 2026 said government funding expires December 11, the lame-duck session is scheduled to end December 17, and an EY adviser named the 48D credit as one candidate for a year-end tax package; a former Senate Finance tax counsel quoted there said a longer-term deal looked "less and less likely" after the midterms [7]. Those are forecasts, not scheduled votes. Until a bill is signed, plan on December 31, 2026.
What the deadline means for fab jobs
The deadline governs when projects must start, while hiring for technicians follows construction and equipment install, often years later. That is why announced plans are not the same as open jobs: check an employer's careers page, not a press release. Our guide on how to become a semiconductor fab technician covers training and BLS pay data.
Not confirmed
- Which specific projects have met the physical work test or 5% safe harbor; companies do not generally publish this, and we have not verified any.
- Whether Congress acts before December 31, 2026, and what any final date would be.
- Any IRS guidance issued after November 19, 2026.
Sources (checked Nov 19, 2026)
- IRS, Advanced Manufacturing Investment Credit.
- Legal Information Institute, 26 U.S. Code section 48D, subsection (e).
- Legal Information Institute, 26 CFR 1.48D-5, Beginning of construction (T.D. 10009, 89 FR 84752, Oct. 23, 2024, as amended 89 FR 92793, Nov. 25, 2024); also on eCFR.
- Federal Register, Advanced Manufacturing Investment Credit Rules Under Sections 48D and 50 (final rule, Oct. 23, 2024).
- Congress.gov, H.R. 3204, BASIC Act (status read through the official Congress.gov API) and introduced text.
- Congress.gov, H.R. 6055, SEMI Investment Act (status read through the official Congress.gov API) and introduced text.
- Thomson Reuters Checkpoint, Veto threat to steer Democrats towards tax oversight next year, policy analysts say (Nov. 19, 2026).
Fabwise is not a tax or legal advisor. Confirm with the statute, the final regulations and a qualified tax professional before relying on any date or test.
Frequently asked questions
Does the 48D credit expire at the end of 2026?
Under current law it stops for new starts: the statute says the credit does not apply to property whose construction begins after December 31, 2026. Projects that began construction by then can still claim it when the property is placed in service later.
Does a project have to be finished by the 48D deadline?
No. The deadline is about when construction begins. The final regulations deem the continuity requirement met if the property is placed in service no more than 10 calendar years after the year construction began.
What counts as beginning construction for Section 48D?
Either physical work of a significant nature (examples in the regulation include excavating for the foundation and pouring concrete pads) or paying or incurring at least 5% of the property's total cost, followed by continuous construction or continuous efforts. Planning, permits, surveys and site clearing do not count.
Has Congress extended the 48D construction deadline?
Not as of November 19, 2026. H.R. 3204 (to 2030) and H.R. 6055 (to 2031) show a latest action of referral to the House Ways and Means Committee on Congress.gov, and a November 19, 2026 Thomson Reuters report lists 48D only as a candidate for a year-end package.
More on this topic: CHIPS Act and Section 48D · All Fabwise guides · How we research · Affiliate disclosure